Claim under review / Power & capacity
Power constraints are slowing data-centre expansion
Electricity supply and grid access may be becoming the binding constraints on new computing capacity.
Current assessment
New evidenceFERC’s decision complicates grid management for data-centre expansion. By striking down PJM's proposal to curtail large loads lacking matching generation, federal regulators prevented discriminatory restrictions from being imposed on facilities. However, rejecting the framework leaves regional connection procedures unresolved. This prolongs regulatory uncertainty across the largest US power market as utilities and developers seek compliant ways to connect massive loads. While operators avoid immediate curtailment mandates, the lack of an approved interconnection process leaves connection queues and grid bottlenecks in place.
Latest development: On October 12, 2026, the Federal Energy Regulatory Commission rejected most of PJM Interconnection’s plan to curtail large loads lacking matching new generation, ruling that the proposed restrictions intruded on state jurisdiction and appeared discriminatory.
- Last material update
- 13 Oct 2026
- Last checked
- 13 Oct 2026
Development history
8 updates-
On October 12, 2026, the Federal Energy Regulatory Commission rejected most of PJM Interconnection’s plan to curtail large loads lacking matching new generation, ruling that the proposed restrictions intruded on state jurisdiction and appeared discriminatory.
FERC’s decision complicates grid management for data-centre expansion. By striking down PJM's proposal to curtail large loads lacking matching generation, federal regulators prevented discriminatory restrictions from being imposed on facilities. However, rejecting the framework leaves regional connection procedures unresolved. This prolongs regulatory uncertainty across the largest US power market as utilities and developers seek compliant ways to connect massive loads. While operators avoid immediate curtailment mandates, the lack of an approved interconnection process leaves connection queues and grid bottlenecks in place.
-
FERC rejects most of PJM’s large load interconnection plan
The PJM Interconnection’s plan for curtailing large loads that don’t have matching new generation intrudes on state jurisdiction and appears to be discriminatory, the Federal Energy Regulatory Commission said.
-
FERC rejects most of PJM’s large load interconnection plan
-
Federal regulators intervened in PJM's backstop power auction, causing delays after the grid operator fell short of reserve margins specifically due to aggressive data center load growth.
The strain of rapid data center expansion on regional power grids is increasingly triggering regulatory friction. PJM, the largest US grid operator, has been forced to delay its backstop power auction after federal regulators intervened over cost allocation concerns. This delay, stemming directly from PJM falling short of reserve margins due to aggressive data center load growth, underscores how grid constraints and regulatory hurdles are complicating capacity planning.
-
FERC chair slams PJM ‘mess’ as country’s largest grid operator delays power auction
PJM had planned to accept offers for backstop power supplies from Sept. 30 through Oct. 21 after falling short of its reserve margin targets amid aggressive data center load growth.
-
FERC chair slams PJM ‘mess’ as country’s largest grid operator delays power auction
-
State governments are increasingly slowing data center development in response to public backlash, while community groups are demanding direct financial compensation from hyperscalers like Microsoft.
Local opposition and state-level interventions continue to impede data center expansion. States are actively slowing development as public sentiment sours, while environmental groups are raising alarms over the health risks of on-site backup generators. Furthermore, community groups are beginning to demand direct financial compensation from hyperscalers like Microsoft, adding new friction and costs to capacity buildouts.
-
The blue-collar AI job market is booming. Will data center backlash make it go bust?
The public has soured on AI data centers and states are slowing development
-
Microsoft goes quiet after church groups ask for 1% of data center costs
Microsoft goes quiet after church groups ask for 1% of data center costs
-
Data center backup power contributes to health risks: report
Federal regulatory actions are allowing on-site generators at data centers and other power plants to release dangerous emissions with fewer checks
-
The blue-collar AI job market is booming. Will data center backlash make it go bust?
-
Alternative power strategies and grid connections are faltering, evidenced by Crusoe abandoning a $1.25 billion turbine plan and a 750-MW Oklo project facing an 18-month delay due to a rejected FERC interconnection complaint.
Power constraints and interconnection hurdles are actively disrupting data center capacity plans. Crusoe has abandoned a $1.25 billion initiative to deploy stationary turbines at AI data centers, highlighting the difficulty of executing alternative off-grid power strategies. Concurrently, a 750-MW Oklo power project in Virginia faces a minimum 18-month delay after federal regulators rejected its plea to be reinstated into the regional grid's interconnection study cycle.
-
Crusoe abandons $1.25B plan to use Boom turbines at AI data centers
Crusoe abandons $1.25B plan to use Boom turbines at AI data centers
-
FERC rejects Oklo complaint seeking to reinstate project to PJM’s interconnection study cycle
The decision affects a 750-MW, mixed technology project in Virginia, which Oklo said would be delayed by at least 18 months if it misses the current interconnection cycle.
-
Crusoe abandons $1.25B plan to use Boom turbines at AI data centers
-
Oracle issued force majeure notices for multiple data center projects (Project Jupiter and New Mexico Stargate) due to potential energization delays, while New Jersey regulators fined a data center for relying on unpermitted gas generators.
Power constraints are causing tangible delays and contractual disputes for hyperscalers, as evidenced by Oracle issuing force majeure notices over potential delays to its 2028 data center projects. Additionally, the reliance on temporary power solutions is facing regulatory backlash, with New Jersey fining a data center over a million dollars for using dozens of gas generators, highlighting the friction between rapid capacity expansion and local environmental enforcement.
-
Oracle sends 'force majeure' notice about data center project — stock drops 3%
Oracle is reportedly looking to delay payment on Project Jupiter if the data center fails to come online in 2028
-
Oracle sends force majeure notice on its New Mexico Stargate data center
The notice would allow Oracle to delay payments should the facility miss its 2028 target to come online.
-
New Jersey fines data center $1.1M after drone pics expose 62 gas generators
New Jersey fines data center $1.1M after drone pics expose 62 gas generators
-
Oracle sends 'force majeure' notice about data center project — stock drops 3%
-
Local opposition to data centers is escalating into a broader political and regulatory issue, with new large-load tariffs emerging nationally and data center power concerns becoming a central theme in Texas state elections.
Power constraints and local opposition are increasingly translating into broad regulatory and political friction across the US. Efforts to curb speculative data center projects are gaining ground through large-load tariffs and shifting state-level policies. Furthermore, data center opposition is becoming a prominent political issue, notably reshaping Texas election races as voters cite concerns over power and utility costs.
-
Efforts to curb data center speculation gain ground across the US
Large-load tariffs and other measures to weed out speculative projects are taking shape. Public backlash to data centers, shifting state-level policies and the utility profit model are complicating those efforts
-
Texas turning blue may hinge on Democrats harnessing data center opposition
Data center opposition is reshaping Texas' 2026 governor and Senate races as voters raise concerns over power, water and utility costs.
-
Efforts to curb data center speculation gain ground across the US
-
Regulatory pushback is actively blocking new power generation, as North Carolina regulators denied Duke Energy's gas turbine request due to insufficient proof of data center demand.
Power constraints are increasingly manifesting as regulatory friction and direct hyperscaler investments in generation. While California previously shifted grid upgrade costs to data centers, new regulatory hurdles are emerging elsewhere. North Carolina regulators denied a utility's request for a new gas turbine, explicitly citing a failure to justify the facility's necessity for data centers. This highlights how regulatory scrutiny over infrastructure costs is actively blocking new power capacity intended for compute expansion, compounded by ongoing local opposition in states like Pennsylvania.
-
North Carolina regulators deny Duke Energy gas turbine request over ‘staggering’ cost, uncertain need
The order called out Duke’s commitment to the White House Ratepayer Protection Pledge, saying it had not established the specific extent to which the proposed facility is intended to serve data centers.
-
Everyone can find a reason to dislike data center construction
Inside two years of fraught AI data center debates in Pennsylvania.
-
North Carolina regulators deny Duke Energy gas turbine request over ‘staggering’ cost, uncertain need
-
State-level regulatory interventions are intensifying, with Texas halting permits and California shifting grid upgrade costs to data centers. In response, hyperscalers are bypassing traditional grid reliance by directly funding nuclear generation.
Power constraints are increasingly manifesting as regulatory friction and direct hyperscaler investments in generation. Texas has halted data center permits, while California is mandating that data centers pay for grid upgrades. Conversely, Texas regulators softened interconnection rules, and Google is directly funding a 50-megawatt nuclear plant, illustrating both the regulatory hurdles and the extreme measures taken to secure capacity.
-
Texas Gov. Abbott orders data center permit halt weeks after issuing moratorium
Texas Gov. Abbott orders data center permit halt weeks after issuing moratorium
-
California tightens rules on AI data center energy and water use
The package of laws requires the California Public Utilities Commission to introduce a new rate classification for data centers while forcing them to pay for upgrades
-
Texas PUC adopts softened rules on data center interconnection
The Public Utility Commission of Texas backed off the standards it proposed in March, eliminating a non-refundable interconnection fee and extending energization milestone deadlines.
-
Kairos Power gets up to $100M from Samsung group to build nuclear reactor for Google
Future Google supplier Kairos Power inked a deal with Samsung C&T to help build its first 50-megawatt nuclear power plant.
-
Texas Gov. Abbott orders data center permit halt weeks after issuing moratorium